700MW Thermal Power Unit Energy Storage Frequency Regulation Project
2026-04-13

Project Overview
This project deploys an Energy Storage System for frequency regulation at Units #1 and #2 (700MW) of Zhuhai Thermal Power Plant in Guangdong, China. The system integrates a Battery Energy Storage System (BESS) with thermal power generation units to enhance grid frequency regulation capability and improve the operational flexibility of the power plant.
By combining thermal power units with fast-response energy storage technology, the project enables more precise and efficient automatic generation control (AGC) and supports participation in grid ancillary service markets.
Project Information
Item | Details |
Project Name | Energy Storage Frequency Regulation Project for Units #1 & #2 of Zhuhai Thermal Power Plant |
Project Type | Thermal Power + Energy Storage Frequency Regulation |
Location | Zhuhai, Guangdong, China |
System Capacity | 10.5MW / 21MWh |
Application | Frequency Regulation / Ancillary Services |
System Functions
• Provide fast-response frequency regulation support for thermal power units
• Improve AGC response speed and regulation accuracy
• Reduce the regulation burden on thermal turbine systems
• Support participation in power market ancillary services
Project Value
• Generate revenue through ancillary service frequency regulation
• Extend the service life of thermal power generating units
• Enhance overall power grid operational stability
• Improve power plant dispatch flexibility
-
Securing Residential Power Supply: N'Djamena Off-grid Microgrid Energy Storage Project2026-04-13
-
Enabling Zero-Outage Production: Bamako Film Blowing Machine Off-grid Energy Storage Retrofit Project2026-04-13
-
Pioneering Stable Industrial Power Supply: Mali Factory High-Power Load Energy Storage Project2026-04-13




WhatsApp
Phone